Verfahren zur Montage eines Zahnstangen-Hebesystems in einem Windturbinenturm, Zahnstangen-Hebesystem und Turmabschnitt für einen Windturbinenturm
Anmelder: Siemens Gamesa Renewable Energy A/S 🇩🇰
Details
- Veröffentlichungs-Nr.
- EP4726206
- Anmeldetag
- 11. Oktober 2024
- Veröffentlichung
- 15. April 2026
- Rechtsraum
- EP
- IPC
- F03D13/10, F03D13/20
Abstract
The present invention relates to a method for installing a rack and pinion lift system in a wind turbine tower. The method comprises the following steps:Providing a first tower section of a wind turbine,fixing a first lift mast at an inner wall of the first tower section,providing a second tower section of a wind turbine,fixing a second lift mast at an inner wall of the second tower section, andstacking the first and second tower sections upon each other and connecting the first and second lift masts, thereby forming a continuous rack.The present invention further describes a rack and pinion lift system that is obtainable by this installation method.Moreover, the present invention relates to a tower section for a wind turbine tower. The tower section comprises a lift mast that is fixed at an inner wall of the tower section via a lift mast support structure. The lift mast support structure is configured to allow for a vertical movement of the lift mast vis-à-vis the inner wall of the tower section.
Anmelder
- Firma
- Siemens Gamesa Renewable Energy A/S
- Land
- 🇩🇰 Dänemark
Spanisches Unternehmen im Bereich erneuerbare Energien, entwickelt und fertigt Windkraftanlagen sowie zugehörige Technologien für Onshore- und Offshore-Windparks.
2.713 Patente in unserer Datenbank
Fachgebiete
Vertreten von
-
SGRE-Association
SGRE-Association · Erlangen