Migrationsvorprüfarbeitsablauf für Hyperkonvergierte Infrastruktur in Hybrider Cloud-Anwendung
Anmelder: VMware LLC 🇺🇸
Details
- Veröffentlichungs-Nr.
- EP4647911
- Aktenzeichen
- EP25173099
- Anmeldetag
- 29. April 2025
- Veröffentlichung
- 12. November 2025
- Rechtsraum
- EP
- IPC
- G06F9/48
Abstract
A method of migrating an executing virtual machine, VM, from a source host computer (150-1) to a destination host computer (170-1), includes the steps of: issuing a first instruction to the source host computer (150-1) to instantiate a dummy VM (154-1) having a plurality of network configurations that match a corresponding plurality of network configurations of a target VM (154-2, 154-3); issuing second instructions to the source (150-1) and destination host computers (170-1) to migrate the dummy VM (154-1) from the source host computer (150-1) to the destination host computer (170-1); determining that the dummy VM (154-1) that has been migrated to the destination host computer (170-1) is able to communicate with the target VM (154-2, 154-3); and in response to determining that the migrated dummy VM (154-1) is able to communicate with the target VM (154-2, 154-3), issuing third instructions to the source (150-1) and destination host computers (170-1) to migrate the target VM (154-2, 154-3) from the source host computer (150-1) to the destination host computer (170-1).
Anmelder
- Firma
- VMware LLC
- Land
- 🇺🇸 USA
US-amerikanisches Softwareunternehmen, das Virtualisierungs- und Cloud-Infrastrukturlösungen entwickelt, darunter virtuelle Maschinen, Server- und Netzwerkvirtualisierung sowie Software für Rechenzentren und hybride Clouds.
229 Patente in unserer Datenbank